Lesson 3 of 4 · Dependencies, parallel work and risk
Schedule connected engineering work
8 minute lesson · 3 checks along the way
Your goal for this lessonCalculate an original dependency-based schedule and use a simple risk estimate without treating it as a certain outcome.
In this lesson 3 sections · 3 checks
Read & understand
Write down what each task needs
The BIRDS project-management guidance discusses scope, roles, resources, communication, risk and quality. An original fictional project applies those ideas to three tasks: a two-day message-definition task, a three-day receiver-fixture task and a two-day integrated check. The integrated check needs both earlier tasks completed.
Assume separate available teams can perform the first two tasks concurrently and that the stated durations include their required resources. Under those assumptions, integration begins after day three and finishes after day five. Adding all task durations would give seven days, but that would describe serial execution rather than this parallel arrangement.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Find which delay changes the finish date
In the fictional schedule, the receiver fixture is the longer prerequisite. A one-day delay to that three-day task moves integration’s start to day four and completion to day six. A one-day delay to the two-day message definition instead still lets it finish alongside the fixture on day three.
That one-day tolerance is specific to these durations and assumptions. If the same person must do both prerequisite tasks, they cannot simply overlap as the exercise assumed. Scheduling depends on dependencies and resource availability, not only on drawing two bars beside each other.
Schedule the fictional dependencies
If resources or dependencies change, recompute the schedule rather than assuming the same overlap.
Open full-size diagram in a new tab: Schedule the fictional dependenciesCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Use risk estimates to inform discussion
For another original fictional planning example, a team assigns a 25 percent chance to a four-day delay. Multiplying probability by impact gives one day of expected delay in this simple model. That is an average across imagined repeated cases, not a prediction that the actual project will lose exactly one day.
A second risk with a different probability, consequence or uncertainty may need a different response. Keep the assumptions beside the estimate and record the responsible person and planned evidence checks. A numerical score helps make a discussion explicit, but does not replace engineering judgment or guarantee which event will occur.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.