Lesson 3 of 3 · Dependencies, float and student handover
Plan the integration path
13 minute lesson · 3 checks along the way
Your goal for this lessonIdentify the critical path in a small integration schedule and define a reproducible handover.
In this lesson 4 sections · 3 checks
Read & understand
Schedule the work that joins the teams
A student satellite mission depends on several kinds of readiness arriving together. A payload can work alone while the bus is unfinished; a ground decoder can pass its own tests while the integrated spacecraft still cannot produce the expected packet. CUBICS makes these relationships especially visible through collaborative development. NASA’s technical-planning guidance describes schedules as networks of dependencies and resources. The small network below is an original teaching example, not the schedule of a selected mission.
Count elapsed days from day zero. Separate teams can work in parallel, and every task starts as soon as its stated predecessors finish. Payload preparation takes five days; bus preparation takes eight; and ground-tool preparation takes four. All three begin at day zero. Integration takes three days and can begin only when both payload and bus preparation are complete. A final two-day end-to-end exercise waits for both integration and the ground tools.
Read & understand
Calculate the earliest finish
The payload finishes at day five and the bus at day eight, so integration starts at the later time, day eight. Three days of integration finishes at day eleven. Ground tools have been ready since day four. The final exercise therefore starts at day eleven and finishes at day thirteen. Adding every task duration would give twenty-two days, incorrectly treating all parallel work as sequential. Looking only at the longest individual task would omit the work that must follow it.
The bus-to-integration-to-exercise chain takes 8 + 3 + 2 = 13 days and determines this schedule’s finish. It is the critical path under our assumptions. The payload can finish as late as day eight without delaying integration, giving its five-day task three days of total float. Ground preparation can finish as late as day eleven without delaying the exercise, giving that four-day task seven days of total float. Float is measured against this network and finish target, not guaranteed spare time in the real mission.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Test which change moves the finish
Shorten payload preparation from five days to three while keeping every other task unchanged. Integration still waits for the bus at day eight, and the project still finishes at day thirteen. Shortening bus preparation to six instead moves integration to days six through nine, then the exercise to days nine through eleven. The faster bus shortens the whole plan by two days because it lies on the controlling chain.
Now return to the original task durations but delay ground-tool readiness until day twelve. Integration still ends at eleven, yet the final exercise must wait until twelve and finishes at fourteen. The controlling dependency has changed. If the same engineer must perform payload and bus preparation, our assumption of unrestricted parallel work also fails; a resource-constrained schedule must be constructed. A critical path is a result of the current durations, dependencies and resources, not a permanent label attached to one team.
Follow the tasks that control the finish
Original dependency network with fixed durations and independent teams. Integration requires both payload and bus; the final exercise requires integration and ground tools. The model excludes rework and resource conflicts.
Open full-size diagram in a new tab: Follow the tasks that control the finishCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Make readiness a repeatable condition
A task called “handover complete” is difficult to schedule if nobody can say what completes it. Define an observable condition: the incoming team can run the recorded test fixture, identify the software and interface versions, reproduce the expected result, and explain where failures are logged. Save unresolved issues with their owners and next checks. Attendance at a meeting or delivery of a folder does not alone establish that the next operators can use the system.
The final exercise should connect a known input to the scientific record through the assembled mission chain. Preserve the configuration, results and exceptions so later changes can be compared against them. Our thirteen-day arithmetic contains no allowance for rework, procurement, shared facilities or launch scheduling, so it is not a forecast. Its value is showing where work depends on other work. A realistic plan then adds the evidence, resources and uncertainty that those dependencies require.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: CSA: CUBICS 2026 mission development guidanceDated August 2026 opportunity: 6U collaboration and up-to-3U streams. Appendix B addresses payload accommodation and end-to-end testing; this course is not application guidance.
- Read: NASA: technical planning and schedulesSection 6.1.1.2.3 explains dependency networks, critical paths, float and resource constraints. The worked schedule is invented.
- Read: NASA: configuration managementIdentify versions, coordinate changes and preserve the tested configuration. Our packet schema is not a CUBICS flight protocol.