Lesson 3 of 3 · Dependencies and shared disruption
Test readiness and resilience
12 minute lesson · 3 checks along the way
Your goal for this lessonUse simple dependency and availability models without turning capacity targets into flight forecasts.
In this lesson 4 sections · 3 checks
Read & understand
Identify the dependencies that determine readiness
A launch campaign brings together hardware, people, facilities and external arrangements. Completing one stream early does not remove a dependency on another. The Pathfinder review highlights communication, responsibilities and coordination across organizations and borders. Those findings suggest a practical analytical question: which tasks can proceed independently, and which cannot finish until another task provides its result? The answer is a dependency network rather than one list of accomplishments.
Consider a fictional classroom project with two parallel streams. Stream A takes six days followed by four more days, so it lasts ten days. Stream B takes eight days. A final three-day integration task can begin only after both streams finish. With an immediate start and unlimited resources for the independent work, total duration is max(10, 8) + 3 = 13 days. These are invented planning values, not a regulatory schedule or a launch countdown.
Read & understand
Find which delay changes the finish
If stream B grows from eight to nine days, the project still finishes in thirteen days because A remains the longer prerequisite. If B grows to twelve days, the finish becomes fifteen days. The original two-day difference is scheduling slack under this particular model. It is not a guarantee against all disruptions, especially if the streams share staff or equipment that the simplified diagram treated as independent.
Now suppose the final integration task reveals a mismatch that requires repeating part of A. The original network no longer describes the remaining work; the plan needs a new dependency and duration estimate. A date calculated from an outdated network can look precise while missing the actual constraint. Keep the configuration of the plan, assumptions about resources and evidence of task completion alongside the forecast, and revise them when the underlying work changes.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Check whether alternatives share the same failure
For an original availability exercise, let two equivalent services have independent availability probabilities 0.8 and 0.7 for a specified opportunity. The probability that neither is available is 0.2 × 0.3 = 0.06, so the probability of at least one is 0.94. Independence and equivalent service are assumptions, not benefits guaranteed by having two company names. The calculation concerns availability, not the probability that a launched rocket reaches orbit.
Introduce a shared condition that closes both options with probability 0.2. When that condition is absent, suppose each option has conditional availability 0.9 and their remaining availability events are independent. At least one works with probability 0.8 × (1 − 0.1 × 0.1) = 0.792. Reporting 0.99 would omit the shared closure. Real diversification requires examining common dependencies as well as counting providers, sites or vehicles.
The longer prerequisite controls the finish
The integration task waits for both streams. The model is a teaching schedule, not a regulatory timetable or launch procedure.
Open full-size diagram in a new tab: The longer prerequisite controls the finishCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Separate capacity, demand and completed delivery
A permitted maximum, a factory’s production capacity and a forecast of customer demand are different quantities. None is automatically the number of flights completed in a year. A useful programme dashboard gives each measure its own unit, period and status. For example, a fictional ceiling of ten operations and demand for four do not imply ten operations will occur; hardware readiness and successful delivery remain further questions.
Read dated strategic objectives as intended future outcomes, then look for later evidence of what was actually achieved. A coherent account of LaunchUK can recognize institutional progress, expose unresolved dependencies and describe why complementary services might improve access. It should also preserve the observed result of each flight. The final exercise is to connect the programme’s ambition to a specific mission requirement, a feasible set of dependencies and evidence strong enough to support the claimed capability.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: UK Space Agency: Pathfinder lessons learnedHistorical recommendations about responsibilities, communication and international coordination; recommendations are not proof of completed improvements.
- Read: UK Space Strategy: assured accessThe 2026 strategy connects domestic polar and Sun-synchronous access with international services for other orbital and lift requirements. Future targets are not completed flights.