Lesson 2 of 4 · Calculate a task schedule from dependencies, shared operators and a closing deadline.
Coordinate two operators
8 minute lesson · 3 checks along the way
Your goal for this lessonCalculate a task schedule from dependencies, shared operators and a closing deadline.
In this lesson 3 sections · 3 checks
Read & understand
An operator needs time to act
NRO’s history explains the intended value of an onboard operator: choosing observations as conditions changed rather than relying only on advance decisions. That was a proposed advantage, not a demonstrated MOL operating record. A person can act only if information, equipment and time are available. The two-person crew envisioned for MOL therefore raises a scheduling question as well as a hardware question.
Our fictional simulator uses two operators and a single observation. Operator A inspects a view for six minutes. Operator B independently configures equipment for ten minutes. Both tasks start at minute zero. A joint readiness check takes two minutes after both tasks finish; a four-minute recording follows. All durations, dependencies and deadlines here are invented classroom inputs, not historical MOL procedures.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Follow the longest dependent chain
The readiness check starts at minute ten, when the slower initial task finishes. It ends at minute twelve, and recording ends at minute sixteen. Written compactly, completion time is max(6, 10) + 2 + 4 = 16 minutes. A deadline at minute eighteen leaves two minutes of slack. Adding all four durations gives twenty-two minutes, but incorrectly treats the independent initial tasks as sequential.
The longest chain, equipment configuration then readiness then recording, sets the earliest finish in this model. If configuration grows from ten to fourteen minutes, completion moves to minute twenty and misses the deadline by two minutes. Reducing the six-minute inspection to four minutes does not improve the original finish: configuration still determines when readiness can start.
Schedule tasks and people
Fictional schedule · not historical MOL procedures.
Open full-size diagram in a new tab: Schedule tasks and peopleCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Check people as well as arrows
Now suppose both initial tasks need the same operator and cannot overlap. Six plus ten minutes must pass before the readiness check, making total completion twenty-two minutes. The earlier parallel schedule is no longer feasible even though the task list has not changed. A second person helps only when the work can actually be divided and the required equipment is available.
Try a separate example: independent initial tasks take nine and seven minutes, readiness takes three, and recording takes five. Completion is seventeen minutes, leaving three before a minute-twenty deadline. These calculations assume exact durations, no interruptions and immediate handoffs. Real planning must examine variability, fatigue and other duties. Positive arithmetic slack is useful, but it does not prove that a crew can sustain the plan for a mission.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: NRO: the intended role of the onboard operatorHistorical account of selecting observations in real time. The scheduling numbers in this lesson are fictional.
- Read: NASA: proposed crews and mission durationThe two-person, 30-day plan provides context; it was not an achieved occupied MOL mission.