The 2021 first flight did not place its dummy payload into the intended orbit. KARI’s English investigation account, published in January 2022, connects the early third-stage shutdown to a helium tank inside the oxidizer tank. Its anchoring did not adequately accommodate increased buoyancy loads during flight.
The account describes detachment and internal damage, followed by leakage and inadequate oxidizer delivery to the engine. This is a chain connecting structure, fluid containment and propulsion. Naming the last observed symptom, an early engine cutoff, is less informative than explaining the supported mechanism that led to it.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
A load depends on the operating environment
A simple buoyancy model multiplies displaced-fluid density by volume and effective acceleration. In an accelerating vehicle, the relevant load condition can differ from the one experienced by stationary hardware. This is a general teaching model, not a calculation of Nuri’s actual tank loads.
Suppose a fictional body displaces 2 kg of liquid. At an effective acceleration of 10 metres per second squared, the modeled buoyant force is 20 newtons. At 20 metres per second squared it is 40 newtons. The displaced mass is the same, while the modeled force doubles. Actual supports must account for the complete load case, including other forces and dynamics.
An original buoyancy-load comparison
Original teaching model with invented inputs. The real support design requires all applicable forces and dynamics, not only the simplified buoyancy term.
Open full-size diagram in a new tab: An original buoyancy-load comparisonCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Tie the correction to the finding
KARI’s March 2022 plan describes stronger lower anchoring and a thicker manhole cover. It also describes disassembling the already-built third stage, applying changes, reassembling it and performing a leak test. A correction changes the configuration, so evidence for the earlier configuration is not enough on its own.
For an original review, trace each proposed change to the problem it addresses, then choose a test that exercises the changed function. A structural modification needs evidence for its loads; a reassembled pressure boundary needs leakage evidence. A later successful flight adds integrated evidence but does not prove that every possible future condition has been tested.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: KARI: Nuri investigation findingsEnglish page dated 24 January 2022 reports the investigation of the 21 October 2021 flight. It links underestimated buoyancy loads to helium-tank detachment, damage and leakage, and premature third-stage cutoff. Preserve publication date separately from the investigated flight.
- Read: KARI: planned corrections for the second flight2 March 2022 account describes stronger lower anchoring, a thicker manhole cover, disassembly/reassembly and subsequent leak testing. Its June dates are a planning window, not evidence of the actual second-flight day.