Lesson 2 of 4 · Visibility, compatibility and transition time
Schedule a feasible contact
8 minute lesson · 3 checks along the way
Your goal for this lessonBuild a feasible contact schedule using visibility windows, resource limits and explicitly stated setup time.
In this lesson 3 sections · 3 checks
Read & understand
Visibility is a necessary starting point
A spacecraft must have a usable path to the station for a direct radio contact. In an invented planning exercise, the mission is geometrically visible from 10:00 to 10:12. The assigned antenna is occupied until 10:03 and takes two minutes to change configuration and acquire the new target. Under these simplified assumptions, useful service begins at 10:05 and has at most seven minutes before the window ends.
The twelve-minute geometric interval is not twelve minutes of usable payload delivery. Equipment availability, compatible configuration, acquisition and link quality matter too. Real contact planning involves more details than this exercise supplies. The fictional schedule isolates the distinction between a possible view of the target and an accepted interval for a particular service.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
A shared resource cannot do incompatible work twice
Suppose a classroom antenna can support only one target at a time. Mission A requires the whole interval 11:00–11:08; Mission B requires 11:06–11:12. The overlap from 11:06 to 11:08 is a conflict. Adding their durations does not create enough antenna capacity. The planner needs a permitted reschedule, another compatible resource or an explicit statement that both requests cannot be met as written.
Now add a two-minute transition after A. Even if B could start at 11:08, the same antenna would not be ready until 11:10. A feasible schedule must include that transition, not simply draw adjacent coloured bars. If B needs four complete minutes before 11:12, this option still fails. Requirements such as a continuous interval must remain attached when alternatives are compared.
Visibility is longer than useful service
Fictional single-resource schedule; no actual SANSA booking is represented.
Open full-size diagram in a new tab: Visibility is longer than useful serviceCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Check the complete resource path
An available dish is not the whole service. Imagine the classroom antenna is free but its required receiver is reserved for a different task, or the onward delivery link is unavailable. The schedule must account for the resources needed by the agreed service. It should not label a contact fully supported simply because one visible component has no booking.
A planning record should identify the target, window, resource assignment, configuration and acceptance criteria. A change then has a clear scope: what is being moved, which constraint is being relaxed and who needs the revised plan? The purpose is to keep commitments achievable and understandable. The example makes no claim about SANSA’s actual bookings, equipment capacities or mission priorities.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: SANSA: Space Operations servicesOperator description of Hartebeesthoek tracking, telemetry, command and ground-segment work; institutional capability is distinct from a live contact schedule.
- Read: NASA: spacecraft telecommunicationsTeaching reference for uplink, downlink and the interpretation of received signals. All course schedules and packet examples are fictional.