Lesson 2 of 4 · Calculate a test schedule with dependencies and a shared facility.
Schedule shared verification
8 minute lesson · 3 checks along the way
Your goal for this lessonCalculate a test schedule with dependencies and a shared facility.
In this lesson 3 sections · 3 checks
Read & understand
Separate work duration from elapsed time
Several missions can compete for the same test facility even when their teams work independently. TASA lists assembly and testing facilities among its industrial services. Their existence does not disclose the startup program’s booking calendar or guarantee an available slot. The following original schedule is deliberately fictional and teaches how a shared resource changes elapsed time.
At time zero, Team A begins four days of preparation and Team B begins two days. Separate teams allow those activities to run concurrently. A then needs three days in one shared test chamber; B needs two days in that same chamber. Each mission needs one further day of analysis after its chamber work. Analysis teams are separate and can work while the other mission uses the chamber.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Allocate the shared facility
Schedule B in the chamber from day two to day four, then A from day four to day seven. B’s analysis finishes on day five and A’s on day eight. Both missions therefore finish by day eight. This meets the lower bound set by A’s own chain: four preparation days plus three test days plus one analysis day.
If the chamber instead waits for A, A uses it from day four to day seven and B from day seven to day nine. Their analyses finish on days eight and ten. The combined finish moves to day ten even though nobody’s work duration changed. Adding all thirteen person-or-facility activity days is also wrong for elapsed time, because some activities overlap.
Schedule the shared test chamber
Original teaching model; not a TASA test plan or measured result.
Open full-size diagram in a new tab: Schedule the shared test chamberCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Revise the schedule when evidence changes
Now suppose B’s preparation actually takes five days. The earlier day-two reservation is no longer feasible. With A ready on day four, one useful revised order puts A in the chamber on days four through seven and B on days seven through nine, finishing both analyses by day ten. A schedule must respect readiness as well as resource availability.
For this simplified exercise, durations are fixed and there is no setup time, maintenance, weekend restriction or failed test. A real plan would document those conditions and reserve appropriate contingency. More satellites create more opportunities to learn, but adding hardware does not automatically add chamber capacity or remove a dependency that gates the work.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: TASA: assembly and testing servicesAgency facility description only; the exercise does not represent actual bookings, durations or program procedures.
- Read: TASA: CubeSat industrial development programProgram purpose, industrial teams and spacecraft/ground/application responsibilities; inconsistent 6U/8U and mass text excluded, old timetable superseded.