Lesson 2 of 4 · Traceable verification and bounded readings
Trace a claim to a test
17 minute lesson · 3 checks along the way
Your goal for this lessonConnect a requirement to a criterion, configuration and result; assess stipulated bounded readings without treating an overlap as a clear pass.
In this lesson 3 sections · 3 checks
Using archive links & definitions
Follow a linked name to explore its archive card. “Back to your lesson” brings you to the same part of the reading.
Read & understand
Make a claim that can be checked
NASA’s product-verification guidance links specified requirements with methods and recorded results. It also distinguishes checking a requirement from assessing usefulness in realistic operation. This is comparison guidance for thinking about evidence; it does not establish that SSTL or GISTDA used NASA’s procedures. Begin by identifying the claim, the article and configuration being checked, and the condition under which the result is meant to apply.
Our fictional unit has four requirements. R1 concerns its supply voltage under a stated load. R2 concerns decoding a specified packet. R3 concerns rejecting an invalid command. R4 concerns preserving a required event record. A voltage reading cannot by itself prove command rejection. A photograph of the assembled unit cannot replace either result. Give each requirement an identifier so that a statement such as “all tests passed” can be traced to the claims it actually supports.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Read a measurement together with its stipulated bound
For R1, stipulate an acceptable interval from 4.80 to 5.20 volts, including both endpoints. Also stipulate a deterministic error bound for each reading: the actual value lies somewhere in the resulting interval. A reading of 4.90 volts with a bound of ±0.04 spans 4.86 to 4.94 volts. Every allowed value is inside the requirement, so the reading supports a pass under these exercise assumptions.
A reading of 5.18 ±0.04 spans 5.14 to 5.22 volts. The displayed centre is inside the requirement, but part of the interval lies outside it; the evidence does not settle compliance. A reading of 5.28 ±0.03 spans 5.25 to 5.31 volts, entirely above the upper limit. That case supports failure. These invented bounds are not confidence intervals, instrument specifications or a prescribed acceptance policy for spacecraft.
Bounded readings against an inclusive requirement
Original deterministic-bound exercise, not THEOS-2A measurements or a statistical uncertainty model. All rows share one voltage scale.
Open full-size diagram in a new tab: Bounded readings against an inclusive requirementRead diagram data as a table
| Reading (V) | Bound (±V) | Lower (V) | Upper (V) | Decision |
|---|---|---|---|---|
| 4.90 | .04 | 4.86 | 4.94 | Within |
| 5.18 | .04 | 5.14 | 5.22 | Overlaps |
| 5.28 | .03 | 5.25 | 5.31 | Outside |
Original deterministic-bound exercise, not THEOS-2A measurements or a statistical uncertainty model. All rows share one voltage scale.
Check 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Preserve enough context to repeat the check
Imagine receiving the number “4.90” in a spreadsheet with no units, load setting or article identifier. Even if the number matches a successful example, you cannot establish that the relevant condition was checked. The test record needs to make the result interpretable: what was connected, what was measured, which criterion was applied and whether anything unexpected occurred.
If the interval overlaps the limit, do not round the central reading until it appears comfortably acceptable. Investigate the measurement arrangement and the requirement’s decision rule, or collect better evidence. If a discrepancy is corrected, retain the earlier result and explain what changed before the repeat. The fictional voltage example teaches an evidence boundary; it does not license substituting arithmetic for a real calibration and verification plan.
Engineering comparison: NASA engineer Kate Gasaway reviews a checklist before BurstCube magnetic calibration testing at Wallops. The visible record illustrates preparation, but the photograph alone cannot establish the configuration, criteria or test result. This is not THEOS-2A hardware.
Look closely
Does the visible checklist establish that this spacecraft passed its test?
See what to notice
No. The photograph documents preparation. A defensible result also needs the requirement, acceptance criterion, identified configuration, conditions and recorded readings. This BurstCube comparison is not evidence about THEOS-2A testing.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: NASA Systems Engineering Handbook: product verificationComparison guidance for requirements, methods, conditions, configuration, results and discrepancy records. Not evidence that THEOS-2A followed a particular NASA process.
- Read: SSTL: THEOS-2 SmallSAT shipment, June 2022June 20, 2022 shipment account: Carbonite-derived small satellite, training and supply-chain qualification; future operations language predates loss. Assembly/testing photo credited SSTL, but reuse rights not established.