Lesson 1 of 4 · Launch, commissioning and service
Separate mission and service milestones
8 minute lesson · 3 checks along the way
Your goal for this lessonDistinguish a spacecraft event from the readiness of a complete communications service.
In this lesson 3 sections · 3 checks
Using archive links & definitions
Follow a linked name to explore its archive card. “Back to your lesson” brings you to the same part of the reading.
Read & understand
A satellite is one part of the service
ABE records Túpac Katari’s launch on 20 December 2013 and commercial service beginning in April 2014. Those dates describe different milestones. The first concerns access to space; the second concerns an operating service. The archive’s Tupac Katari record connects the named spacecraft to its broader mission history.
For an original classroom project, imagine that a relay reaches orbit while its customer gateway is still being tested. The launch can be complete even though the customer service is not ready. A useful timeline gives each milestone a name, an event date and supporting evidence instead of calling every stage simply operational.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Give commissioning its own place
The historical strategy describes orbital transition, in-orbit tests and handover before commercial operation. Commissioning bridges delivery and routine use: the team checks whether the installed system performs its intended functions. A published sequence is stronger evidence than a guess based only on the launch date.
In a fictional acceptance exercise, three requirements are listed: track the satellite, carry a test message through the gateway and deliver a message to an installed customer terminal. Passing the first two does not establish the third. Write a separate result for each requirement, including the configuration and date, so readiness can be assessed at the right scope.
Different milestones need different evidence
A completed earlier stage does not automatically establish every later one.
Open full-size diagram in a new tab: Different milestones need different evidenceCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
A planned lifetime is not an expiry event
ABE’s technical sheet gives an estimated service life. An estimate expresses a design or planning expectation; it is not a dated observation of the final day of operation. A calendar calculation alone cannot establish either an early failure or an extension. Later operating records are needed for those claims.
Practice with a fictional spacecraft described in an old brochure as designed for twelve years. A historian reviewing year thirteen should seek a dated operator status report. The old design target remains part of the history, but it cannot answer the present-status question by itself. The same care applies when a launch schedule has elapsed without a confirmation report.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: ABE: Túpac Katari communications systemOperator description of launch, commercial service, Amachuma and La Guardia, frequency bands and geostationary operation. Coverage and estimated lifetime are stated capabilities and planning information, not a guarantee of every user’s current service.
- Read: ABE: 2016–2020 institutional strategyHistorical institutional account, especially printed pages 10–12: commissioning, commercial-service start and complementary ground infrastructure. Read statements in their publication period; scheduled work is not automatically a completed event.