Compare costs with the same scope
8 minute lesson · 3 checks along the way
Your goal for this lessonCalculate a reserve and compare a cost estimate with a cap covering the same items.
In this lesson 3 sections · 3 checks
Read & understand
A number needs a boundary
In September 2015, NASA announced five Discovery concept studies and described a possible selected mission cost of approximately $500 million excluding launch and post-launch operations. The exclusions are essential to interpreting the number. That historical figure is not a current universal Discovery limit, a final accounting of every selected mission, or the price of an entire launch-to-archive investigation.
A fair comparison names the activities included, the price-year basis, the units and the treatment of uncertainty. A launch-inclusive lifetime estimate cannot be compared directly with a development-only cap. Selection for a concept study also does not mean that a proposal has been selected for flight. Each stage answers a different decision.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Reserve belongs inside the defined total
Use fictional budget units, all stated in one common price year. The exercise cap is 320 units and covers the 255-unit base estimate plus a reserve equal to 20% of that base. Launch costs 40 units and post-launch operations cost 30 units; both are explicitly outside this exercise cap. Reserve is 0.20 × 255 = 51 units. The amount compared with the cap is therefore 255 + 51 = 306 units, leaving 14 units of headroom.
The sum of all listed activities including reserve is 306 + 40 + 30 = 376 units. That larger sum does not violate a cap that explicitly excludes launch and operations. It also should not be labeled a complete real mission cost: this exercise lists only its defined categories. Headroom under the cap and the 51-unit reserve are different quantities. Neither guarantees that unforeseen work will fit.
Match the estimate to the cap
Original diagram with fictional teaching inputs; actual mission requirements and accounting depend on the applicable documents.
Open full-size diagram in a new tab: Match the estimate to the capCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Keep uncertainty visible when the estimate changes
If the same fictional base estimate rises to 275 units and the reserve rule remains 20% of the base, reserve becomes 55 and the capped total becomes 330. That exceeds 320 by 10 units. Reusing the earlier 51-unit reserve would silently change the agreed calculation. Treating the reserve as free money outside the cap would change the scope of the comparison.
A cost review should connect uncertain work to the estimates and reserves that address it. It should also state which items are excluded and who must provide them. Passing an arithmetic cap check is only one condition: the mission still needs credible technical plans, a schedule and the ability to deliver its required science.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: NASA: Discovery concept selections, September 2015This historical announcement explicitly excluded launch and post-launch operations from its stated mission cap.
- Read: NASA: Discovery 2019 Phase A guidelines, amended July 2020PDF pages 11–12 discuss usable science data, resiliency and verifiable requirements. These are historical competition documents.