Lesson 4 of 4 · Evaluate baseline and threshold science separately from additional opportunities.
Judge completion before adding an extension
8 minute lesson · 3 checks along the way
Your goal for this lessonEvaluate baseline and threshold science separately from additional opportunities.
In this lesson 3 sections · 3 checks
Using archive links & definitions
Follow a linked name to explore its archive card. “Back to your lesson” brings you to the same part of the reading.
Read & understand
Additional science has its own objective
NEAR Shoemaker completed its prime science objectives before the controlled descent to Eros on February 12, 2001. NASA’s contemporary account describes obtaining close-up images as the first priority of the descent and a safe landing as the second. A successful landing therefore added an opportunity after the prime investigation; it was not a missing prime requirement that the team quietly removed.
A mission extension can exploit remaining capability, but its result should be labeled separately from the requirements used to judge the original mission. Extra images do not automatically repair a missing measurement of a different kind. The history of one successful controlled descent also does not establish that another orbiter can land safely.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Use requirements fixed before the result
Historical Discovery guidelines distinguished a baseline science mission from a threshold science mission and asked for clear, verifiable requirements. For this fictional exercise, baseline requires qualifying measurements of eight named targets AND a released, documented calibration archive. Threshold requires qualifying measurements of at least six of those targets AND the same archive. Every target counted must meet the specified measurement-quality rule.
Suppose seven targets have qualifying measurements and the calibration archive has been released. Threshold is met, but baseline is incomplete because the eighth target is missing. If the archive has not been released, neither set of requirements is fully met, even with all eight targets measured. The AND condition matters: a large count in one category does not compensate for a required deliverable in another.
Check every required deliverable
Original diagram with fictional teaching inputs; actual mission requirements and accounting depend on the applicable documents.
Open full-size diagram in a new tab: Check every required deliverableCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Report achievement without rewriting the goal
If an optional experiment later observes a ninth, unlisted target, that result may be valuable. It does not replace the absent eighth named target unless a formal change to the requirements is approved and recorded. Keep the original requirement, the approved change if any, and the actual result distinct so a reader can understand what was delivered.
A threshold is useful for planning a coherent reduced investigation before trouble occurs. It should not become a label invented after a shortfall to imply that every baseline objective succeeded. A careful completion report identifies measured targets, qualifying data, archive delivery, remaining gaps and additional science. That makes the achievement understandable without diminishing the value of real discoveries.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: NASA: NEAR Shoemaker’s landing exceeds expectationsThe February 2001 account states that prime science objectives were complete before the controlled descent.
- Read: NASA: Discovery 2019 Phase A guidelines, amended July 2020PDF pages 11–12 discuss usable science data, resiliency and verifiable requirements. These are historical competition documents.