Lesson 3 of 4 · Dependencies and transport stages
Plan the path to release
8 minute lesson · 3 checks along the way
Your goal for this lessonCalculate a fictional integration schedule and distinguish cargo ascent from independent deployment.
In this lesson 3 sections · 3 checks
Read & understand
Draw the dependency before adding time
A spacecraft cannot enter a shared activity until its prerequisites are ready. In an original schedule, the hardware check takes four days and a documentation review takes six days. They start together, and both must finish before a two-day integration task begins.
The earliest completion is eight days: the slower six-day prerequisite followed by two days of integration. Adding four, six and two would incorrectly place the parallel work in sequence. This simplified exercise excludes queues and uncertainty; it is not a launch forecast.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Find which delay changes the finish
If the four-day hardware check slips by one day, it still finishes before the six-day document review. The modeled finish remains day eight. If the review instead takes eight days, integration cannot begin until then and completion moves to day ten.
The controlling dependency can change as a project changes. Track what each task waits for, then recalculate the finish using the actual dependencies. An early completion in one branch cannot automatically compensate for a delay in another branch that integration still needs.
Parallel prerequisites before integration
Original dependency model; queues and uncertainty are excluded.
Open full-size diagram in a new tab: Parallel prerequisites before integrationCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Keep ascent and release separate
A CubeSat carried to the station travels as cargo before release through the deployment system. TUMnanoSAT provides a completed KiboCUBE example: the university described transport stages, and JAXA later confirmed its 12 August 2022 release. Arriving aboard a cargo vehicle and beginning independent flight are different events.
In a mission ledger, use separate entries for integration, cargo ascent, arrival and deployment, with the supporting source for each. This avoids using a carrier launch photograph as proof of a later CubeSat release. The program’s educational purpose remains connected to the actual engineering and operations sequence.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: UNOOSA: KiboCUBE program and awardeesProgram-provider account reviewed 3 November 2026: institutional roles, awardee rounds and deployment news. Selection and completed deployment are distinct milestones; this is not application or eligibility advice.
- Read: Technical University of Moldova: engineering and experiment purposesUniversity account dated 18 February 2022 describes participating disciplines, development and intended sensors, communications and power experiments. Its future transport and release stages are plans at publication.
- Read: JAXA: TUMnanoSAT deployed from Kibo17 August 2022 account confirms the 12 August deployment, 1U spacecraft, university and KiboCUBE relationship. Listed technology demonstrations are mission purposes, not a complete results report.