Lesson 2 of 3 · Peak power, energy and usable capacity
Fit a payload within two power limits
12 minute lesson · 3 checks along the way
Your goal for this lessonCheck instantaneous power and accumulated energy separately when planning a hosted payload sequence.
In this lesson 4 sections · 3 checks
Read & understand
A capable instrument still needs a usable operating plan
A LEAP-supported payload can join a host supplied by another organization. Its scientific capability must fit the host’s accommodation and operating constraints. A demonstration plan therefore needs more than a statement that the payload works on a laboratory bench. It must describe when it runs, what resources it draws, what it returns and how that behavior fits the larger system. The historical capability-demonstration opportunity explicitly connects development with delivery and integration.
This lesson uses an invented camera, transmitter and battery to examine two constraints that are often confused. Peak electrical power limits the load at a particular moment. Stored energy limits the accumulated consumption over the sequence. A plan can satisfy one and violate the other. All numbers below are classroom values, not specifications of a LEAP instrument, Blue Ghost or a Canadian rover.
Read & understand
Check the simultaneous loads
The host allows at most 12 watts during the exercise. Housekeeping draws 2 W whenever the payload is on. A camera adds 8 W while collecting, and a transmitter adds 6 W while sending data. Running all three together draws 2 + 8 + 6 = 16 W, exceeding the allowance by 4 W. An average below twelve over a longer period cannot remove that instantaneous violation.
Instead, collect for ten minutes with housekeeping and camera, then transmit for five minutes with housekeeping and transmitter. The respective loads are 10 W and 8 W, both below the 12-W limit. This sequencing removes simultaneous operation, but it requires enough storage for the collected data and must still meet the observation and communication timing needs. A power calculation alone does not establish that those other constraints are satisfied.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Integrate the load and reserve the usable energy
The first phase consumes 10 × 10/60 = 5/3 watt-hours. The second consumes 8 × 5/60 = 2/3 Wh. Together they require 7/3 Wh, about 2.333 Wh. The model counts housekeeping in both phases. Adding only camera and transmitter energies would omit a load that continues throughout the operation. Keep units consistent: watts multiplied by hours give watt-hours, while watts multiplied by minutes require division by sixty.
Suppose the battery has 5 Wh of nominal energy. Under the stated operating condition, a modeled derating leaves 80 percent, or 4 Wh, available. The plan reserves 1 Wh for other required operations, leaving 3 Wh for this sequence. Its energy headroom is 3 − 7/3 = 2/3 Wh. Comparing the sequence with the full 5 Wh would overstate its available margin because it ignores the derating and the explicitly reserved energy.
Peak power and energy both have to fit
Original sequence and battery assumptions, not flight specifications. Resource checks also need storage, timing, environment and the host’s agreed definitions.
Open full-size diagram in a new tab: Peak power and energy both have to fitCheck 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Recheck a revised science request
Extend collection from ten to fifteen minutes while leaving transmission at five. Peak power remains 10 W during collection and 8 W during transmission, so the instantaneous check still passes. Energy becomes 10 × 15/60 + 8 × 5/60 = 19/6 Wh, about 3.167 Wh. That exceeds the 3-Wh allocation by 1/6 Wh. A longer observation can therefore break the energy constraint without changing the maximum load.
Actual integration also needs transient behavior, conversion efficiency, temperature dependence and the host’s documented resource definitions. Our simplified derating is given as an assumption, not a measured battery characteristic. Link the agreed operating modes to a reproducible integrated test and the correct configuration. For a demonstration program, the useful evidence is that the contribution can perform its intended task within the complete host constraints, with the remaining uncertainties made visible.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: CSA: LEAP capability demonstration opportunity, 2020–2022Historical objectives connect payload development with delivery, integration and demonstration. Closed application dates are not current guidance.
- Read: NASA: product verificationConnect each requirement with suitable evidence from the identified configuration and conditions.