Lesson 4 of 4 · Reconstruct a dated handoff while preserving completed, pending and later-reported work.
Handoff unfinished work
8 minute lesson · 3 checks along the way
Your goal for this lessonReconstruct a dated handoff while preserving completed, pending and later-reported work.
In this lesson 3 sections · 3 checks
Read & understand
Put the milestones in their own years
The public abstract of NSPO’s 2010 annual report dates CKUTEX’s integration-and-testing readiness review to June 28, 2010. TASA’s later history records closure of the agency’s independent microsatellite program in 2010 and transfer of remaining CKUTEX work to the university. Readiness for an activity, program closure and transfer of responsibility are distinct events.
A university-authored report for the 2014 UNISEC-Global meeting later describes CKUTEX as integrated, tested and ready for launch. That statement documents what its authors reported at that time. It does not establish a launch, every individual test condition or the spacecraft’s present state. The later account prevents treating agency closure as proof that all university development stopped.
Read each milestone within its dated scope
Sources: NSPO annual-report abstract, TASA and NCKU’s UNISEC report.
Open full-size diagram in a new tab: Read each milestone within its dated scopeCheck 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Make the receiving team’s uncertainty visible
Consider an original fictional handoff with four required checks. Three signed records match the delivered article and its configuration; the fourth required result is absent. The receiving team can credit the three covered checks and must leave the fourth unverified. An absent result is neither a recorded pass nor a recorded failure.
A useful handoff identifies the article, its hardware and software versions, the source of each result, unresolved discrepancies, responsible team and next action. Suppose a loose folder contains a passing test but its serial number belongs to a different article. That result may still have engineering value, yet it cannot be filed as direct acceptance evidence for the delivered unit without a justified applicability assessment.
Check 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Continue the record without rewriting the past
In the fictional project, the missing check is performed after transfer and passes in a revised configuration. Record its new date, version and result. Keep the earlier handoff entry showing that the check was open then. A history that preserves both states explains progress; replacing the earlier gap with a backdated pass would erase what the receiving team actually knew.
The Taiwanese program illustrates why a handoff needs more than a single finished-or-canceled label. Keep CKUTEX and FORMOSAT-6 distinct, connect instrument claims to their named project, and record which physical or numerical model supports a result. Later progress can be recognized without converting a readiness statement into a flight report.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.
Explore further · Optional
Go to the source
Explore the evidence behind this lesson. These optional readings and videos open in a new tab.
- Read: TASA: independent microsatellite programDistinguishes experimental CKUTEX and mission-oriented FORMOSAT-6, agency closure and university handoff.
- Read: NSPO 2010 annual report: CKUTEX and E-VACPublic primary-report abstract dates CKUTEX’s integration-and-testing readiness review to June 28, 2010. Full annual-report pages are not reproduced here.
- Read: NCKU authors: 2014 university space-education reportVannitsen, Juang and Miau report CKUTEX integrated, tested and ready for launch. This dated status is not a flight report or present-day readiness guarantee.
- Read: NASA: product verificationGeneral guidance on requirements, test articles, configurations and methods; not a CKUTEX test report.