Lesson 4 of 4 · Operating requirements and reproducible evidence
Test the operating plan
16 minute lesson · 3 checks along the way
Your goal for this lessonBuild a bounded evidence plan that tests timing and assumptions while preserving useful work for another team.
In this lesson 3 sections · 3 checks
Read & understand
Turn a desired outcome into a check
For our fictional exercise, write the requirement before choosing a schedule: supply every requested task and keep stored energy at or above 1 watt-hour throughout the ninety-minute window. Sun-first meets that requirement under the stated assumptions; dark-first does not. A requirement that only checked the final value would miss the problem we intended to prevent.
NASA’s product-realization guidance distinguishes checking a product against its specifications from checking whether it serves the intended use. It also calls for understanding test limitations and assumptions. Applied here, a correct energy calculation and an adequate operating requirement are separate questions: a perfectly implemented final-charge check can still answer the wrong question.
Two conditions for accepting the fictional schedule
Original idealized exercise. Require every requested task to be supplied and storage to remain at or above 1 Wh throughout. Passing this model is not hardware or flight validation.
Open full-size diagram in a new tab: Two conditions for accepting the fictional scheduleRead diagram data as a table
| Schedule | Minimum stored (Wh) | Unmet (Wh) | All demand served | Reserve retained | Combined result |
|---|---|---|---|---|---|
| Sun-first | 2 | 0 | Pass | Pass | Pass |
| Dark-first | 0 | 0.5 | Fail | Fail | Fail |
Original idealized exercise. Require every requested task to be supplied and storage to remain at or above 1 Wh throughout. Passing this model is not hardware or flight validation.
Check 1 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Challenge the favorable assumptions
Repeat the calculation with a smaller initial amount, a longer dark interval, a different radio start time or lower usable generation. Change one assumption at a time when trying to understand its effect. Keep a record of the changed input and the resulting minimum, discarded energy and unmet demand. Passing one nominal schedule does not establish the behavior of all alternatives.
The exact arithmetic in this course was compared with a separate one-minute ledger for 164 schedules with minute-aligned task boundaries. That agreement is evidence about these calculations. It is not a battery test, proof of SS-1 performance, or coverage of arbitrary sub-minute switching. A hardware-facing analysis would also need justified efficiencies, power constraints, environmental conditions and actual control behavior.
Check 2 of 3
10 pointsUse the reading above. You can try again without losing points.
Read & understand
Leave an explanation another team can use
Imagine receiving a spreadsheet headed “energy budget passed” with no initial charge or task times. You cannot reproduce the claim. A useful handover includes the chronological inputs, units, storage rules, requirement, calculation version and both passing and failing cases. Keep requested and served energy separate so a later reader can identify a shortage without reconstructing hidden assumptions.
This exercise connects back to a university satellite programme through the work a team can retain: a repeatable method, evidence about its limits and a clear account of what remains to be demonstrated. The flight milestone matters, but useful engineering knowledge must also survive the handover. Preserve the reasoning behind a result as carefully as the result itself.
Check 3 of 3
10 pointsUse the reading above. You can try again without losing points.
Put it together
Your lesson progress
Each check connects to a part of the story. Complete all 3 to earn your 25-point lesson bonus.